Perry’s Sadie Heights Drainage Plan Takes Its Next Step 💧

Editorial illustration of a smiling raindrop beside a miniature town on an open book with Perry Good Ideas Flow Here lettering.
Conceptual editorial illustration about Perry stormwater planning; not a photograph or plan of the Sadie Heights project.

Room for the rain: that’s the idea behind Perry’s next planned drainage improvements for Sadie Heights. The city is seeking bids for work that would expand stormwater storage and improve nearby drainage channels. 💧

The date to circle is October 19, 2026, at 11 a.m., when sealed bids are due for the Flood Improvement Project Phase 2A. Addendum 3, dated October 13, moved the deadline to October 19. If you’ve been following along, give that calendar entry a refresh! 📅

Where the water gets more elbow room

Phase 2A calls for excavating and grading part of a regional stormwater pond and improving drainage channels between Stonegate Trail and Rocky Road. The project summary puts the work in Perry’s Stonebridge subdivision off Highway 341, between lot 18 on Stonegate Trail and lot 75 on Rocky Road.

The intended benefits are additional flood storage and better drainage for Sadie Heights and the surrounding area. More room to hold stormwater is the aim; the plans don’t promise an end to flooding.

One pond, two pieces of the puzzle

The remaining portion of the pond is Phase 2B, assigned separately to the developer of the future Avion Park subdivision. The plan anticipates both phases proceeding at the same time, with the city’s contractor and the developer’s contractor coordinating their work. Neighboring projects need to be good neighbors, too!

Next stop: the bid opening

The bid documents call for a public opening at 1211 Washington Street in Perry after the October 19, 11 a.m. deadline. From there, the milestones to watch are the bid outcome, a contract award and a construction schedule.

For now, this is the bidding chapter: the documents don’t establish an awarded contract, a project cost, work underway on either phase or actual start and calendar completion dates. For Sadie Heights neighbors, the next useful news is who will do the work and when.

Sources